Turn off your brain...

I really hate doing this kinda of thing, but sometimes you just need Project to turn its brain off.  I have a peculiar case where I want a start date/time to NEVER change and not be effected by the scheduling algorithms (to include calendar exceptions).  Here is the VBA:

SetTaskField field:="Constraint Type", value:="Must Start On", TaskID:=currentTask.ID
SetTaskField field:="Task Calendar", value:="24 Hours", TaskID:=currentTask.ID
SetTaskField field:="Ignore Resource Calendar", value:="Yes", TaskID:=currentTask.ID

currentTask.Start = startDate